GENERAL ASSEMBLY OF NORTH CAROLINA
SESSION 2013
SESSION LAW 2013-232
SENATE BILL 635
AN ACT to clarify that only incumbent providers may construct a new electricity transmission line.
The General Assembly of North Carolina enacts:
SECTION 1. G.S. 62-100 reads as rewritten:
"§ 62-100. Definitions.
As used in this Article:
(1)
The term "begin to construct" includes any clearing of land,
excavation, or other action that would adversely affect the natural environment
of the route of a transmission line; but that term does not include land
surveys, boring to ascertain geological conditions, or similar preliminary work
undertaken to determine the suitability of proposed routes for a transmission
line that results in temporary changes to the land; land.
(2)
The word "county" means any one of the counties listed in
G.S. 153A-10; G.S. 153A-10.
(3)
The word "land" means any real estate or any estate or interest in
real estate, including water and riparian rights, regardless of the use to
which it is devoted; devoted.
(4)
The word "lines" means distribution lines and transmission lines collectively;
collectively.
(5)
The word "municipality" means any incorporated community, whether
designated as a city, town, or village and any area over which it exercises any
of the powers granted by Article 19 of Chapter 160A of the General Statutes;
Statutes.
(6) The term "public utility" means any of the following:
a. A public utility, as defined in G.S. 62-3(23).
b. An electric membership corporation.
c. A joint municipal power agency.
d.
A city or county that is a person, whether organized under the laws
of this State or under the laws of any other state or country, engaged in
producing, generating, transmitting, delivering, or furnishing electricity for
private or public use. use, including counties, municipalities, joint
municipal power agencies, electric membership corporations, and public and
private corporations; and
(7) The term "transmission line" means an electric line designed with a capacity of at least 161 kilovolts."
SECTION 2. G.S. 62-101(a) reads as rewritten:
"(a) No public utility or any other person may begin to construct a new transmission line without first obtaining from the Commission a certificate of environmental compatibility and public convenience and necessity. Only a public utility as defined in this Article may obtain a certificate to construct a new transmission line, except an entity may obtain a certificate to construct a new transmission line solely for the purpose of providing interconnection of an electric generation facility."
SECTION 3. This act is effective when it becomes law and applies to certificates of environmental compatibility and public convenience and necessity issued on or after that date.
In the General Assembly read three times and ratified this the 27th day of June, 2013.
s/ Daniel J. Forest
President of the Senate
s/ Thom Tillis
Speaker of the House of Representatives
s/ Pat McCrory
Governor